What is Estimate at Completion (EAC) in Project Management?

In project management, Estimate at Completion (EAC) forecasts the project finances at the same time as the project is in progress. Like BAC (Budget at Completion), it is miles part of earned cost control. Unlike BAC, EAC takes into consideration variables like unplanned prices and misguided or out-of-date early estimates.

Estimate at Completion tells us whether events, developments, or barriers have modified the at first envisioned prices of the project. Its elements withinside the Actual Cost of the project to date, in addition to an estimate of closing prices for a greater dynamic image of the project finances.

For example, a project has envisioned BAC to be $15,500. However, the unavailability and transport delays of a few mainly vital fabrics force up prices. Using an EAC component, you may create a brand-new finance forecast primarily based totally on this context.

What are the Estimate at Completion components and the way do you realize which EAC components to use?

The suitable EAC project management components can vary, relying on the situation. Four formulae may be used to calculate EAC.

When the preliminary estimates have been wrong, are actually out of date, or cannot be used as a correct forecast, use the subsequent components:

EAC = AC + ETC
(Estimate at Completion equals Actual Cost plus Estimate to Complete)

When overall performance is regular and has now no longer deviated too sharply from the authentic estimate, use the subsequent components:

EAC = BAC/CPI
(Estimate at Completion equals Budget at Completion divided through Cost Performance Index).

When there have been a few overall performance problems or one-time barriers withinside the project, however, the relaxation of the authentic finances is anticipated to stay correct use the subsequent components:

EAC = AC + (BAC – EV)
(Estimate at crowning glory equals Actual Cost-plus Budget at Completion minus Earned Value)       

When it is miles essential to account for value and agenda if you want to arrive at an up-to-date finance forecast, use this component:

EAC = AC + (BAC – EV)/SPI + CPI
(Estimate at Completion equals Actual Costs plus Budget at Completion minus Earned Value divided through Schedule Performance Index and Cost Performance Index)

In our preceding example, the BAC was $15,500 however a few barriers drove up prices. At 50% project crowning glory, the AC was $8,500 in place of the projected $7,750. In this case, we will use the EAC = AC + (BAC – EV) components due to the fact we assume that the closing finances are correct however ought to account for the preceding overall performance problems.

EAC = 8,500 + (15,500 – 7,750)
EAC right here is $16,250.

Essentially, the EAC will increase through the quantity of the real value handed in the preliminary finances.

Forecasting is a vital part of the project management technique and now no longer ends are essential as soon as the project has commenced. Your project forecasts must no longer be a static device and must, instead, be adjusted because the project progresses.